Creating a One Time Job that Several Days

Collapse
X
  • Filter
  • Time
  • Show
Clear All
new posts

  • Creating a One Time Job that Several Days

    How do I go about creating a one time job for a customer that lasts several days. Such as building a retaining wall. I tried the custom creation of the job but I could not build dates 4 days out from the starting date. What I did was to enter 4 consecutive days of One Time Jobs. That worked, however I am looking for a short cut. Thank you.
    Mark

  • #2
    Hi markf,

    Quote[/b] ]What I did was to enter 4 consecutive days of One Time Jobs. That worked, however I am looking for a short cut.
    Another idea is you could create a custom job with the interval of 1 day. Then ener the start and end dates.

    Comment


    • #3
      Thank you. That was the solution. What I did was put in the interval as 4 days not 1 day.