  • Mass Reschedule: How does it work

    What is the easiest way to reschedule custs you have missed ontheir scheduled day. I can move one day for a postpone but what if you are late by like 2-3days. It throws off the future scheduled days the program created for that cust. For that matter 9-12 customers if you missed a days worth.

  • #2
    Hi Cruzen,

    When you schedule jobs did you know you can set a "minimum days between visit"? Only if you use the custom job schedule option.

    How does this help you?

    Well say you set a job to occur only on mondays. You also set the minimum amount of days between jobs to 6. If you have to postpone a job a couple of days, it wont reappear until at least after 6 days which would be the following monday.

    Does this help?