I would like to know how to schedule a customer for two weeks while they are on vacation. Because the job is snow removal, (charging per time) we dont know when or if it will snow. She wants to have it done if required between april 15 and april 25. How would I schedule this to print with the other jobs only during this time when, and if, it snows?http://www.gophergraphics.com/forum/iB_html/non-cgi/emoticons/rock.gif Thank you.

Gopher Support
04-17-2007, 12:37 PM
You could schedule a daily job that appears each day from April 15-April 25 and called the job "snow removal - if necessary". Just ignore the job each day if it wasn't completed or delete the job date.

Freshcut
04-26-2007, 01:00 AM
Sounds good thanks.